17th January 2019

Progress on Wandsworth Riverside Quarter 6b London

The installation of this £11.7m facade for Fraser Properties and Galliford Try continues to install at pace with fabrication of the 134 steel Balconies now in full progress as the façade progresses and awaits their installation. Schuco windows and curtain wall is installed and exterior cladding is following on. The project is due to complete in the summer of 2019.